Data centers in Jackson County, MO
Existing and planned data centers in Jackson County, Missouri, mapped from the public record with capacity, operators, and impact scores.
3
total
2
planned
0
operating
0
contested
Combined capacity 910 MW — roughly the power of 682,500 homes.
All facilities
| Facility | Status | Operator | Capacity | Impact |
|---|---|---|---|---|
| Nebius Data Center Independence | Under construction | Patmos | 880 MW | 54 |
| Revitalization Unlimited Data Center Kansas City | Cancelled | — | 30 MW | 17 |
| Patmos Data Center Independence | Proposed | — | — | — |
Frequently asked questions
- How many data centers are in Jackson County, MO?
- We track 3 data centers in Jackson County — 0 operating and 2 planned or under construction.
- Are there proposed data centers in Jackson County?
- Yes — 2 are planned or under construction here.
- How much power would these data centers use?
- Their combined disclosed capacity is about 910 MW.