Data centers in Michigan
Existing and planned data centers across Michigan, mapped from the public record with capacity, operators, and impact scores.
29
total
17
planned
4
operating
0
contested
Combined capacity 6,517 MW — roughly the power of 4,887,375 homes.
All facilities
| Facility | Status | Operator | Capacity | Impact |
|---|---|---|---|---|
| Panattoni Project Cannoli Van Buren Township | Proposed | 1,850 MW | 76 | |
| Related Digital/The Barn Saline | Under construction | Related Digital/Open AI/Oracle | 1,400 MW | 49 |
| Lower Peninsula Data Center Lower Peninsula | Proposed | — | 1,000 MW | 47 |
| Kalkaska Data Center Kalkaska Township | Cancelled | — | 1,000 MW | 42 |
| Switch Pyramid Data Center Caledonia | Under construction | Switch | 320 MW | 32 |
| Lyon Township Data Center/ Project Flex New Hudson | Proposed | Verrus/Anthropic | 363 MW | 29 |
| Comcast Southgate | Operating | Comcast | — | — |
| Oppidan Data Center Apple Valley | Cancelled | — | 275 MW | 22 |
| Harbor Farmz Data Center Kalamazoo | Proposed | — | 1 MW | 21 |
| Liquid Web, Inc Lansing | Operating | — | — | — |
| Southfield Data Center Farmington Hills | Proposed | Metrobloks | 100 MW | 20 |
| US Signal Data Center Belleville | Operating | — | 2 MW | 20 |
| Solstice Data Center Allen Park | Blocked | Solstice | 26 MW | 18 |
| Oakland University Data Center Rochester | Proposed | — | 26 MW | 17 |
| University of Michigan Los Alamos Data Center Ypsilanti | Proposed | Los Alamos National Laboratory | — | — |
| Deep Green Data Center Lansing | Cancelled | Deep Green | 24 MW | 16 |
| Microsoft Caledonia Data Center Caledonia | Proposed | Microsoft | — | — |
| Hyperscale Data Michigan Data Center Dowagiac | Operating | — | 30 MW | 14 |
| Alterra Development Corporation Data Center Marshall | Proposed | Alterra Development | — | — |
| Microsoft Grand Rapids Data Center Grand Rapids | Proposed | Microsoft | — | — |
| Kalamazoo County Data Center Kalamazoo | Blocked | — | — | — |
| Charlevoix Big Rock Data Center and Small Modular Nuclear (pre-proposal) Charlevoix | Proposed | Holtec | — | — |
| Project Peninsula Cedar Springs | Proposed | Venerly LLC? | — | — |
| Thor Equities Data Center Augusta Township | Proposed | — | — | — |
| Microsoft Dorr Data Center Dorr | Proposed | Microsoft | — | — |
| Lowell Covenant Business Park Data Center Lowell | Blocked | Franklin Partners/Microsoft | 100 MW | 9 |
| Washington Township Data Center Washington Township | Proposed | Prologis | — | — |
| Cloverleaf Infrastructure Data Center Dundee | Blocked | — | — | — |
| Howell Data Center Fowlerville | Cancelled | Santec Consulting/Meta | — | — |
Frequently asked questions
- How many data centers are in Michigan?
- We track 29 data centers in Michigan from public records — 4 operating and 17 planned or under construction.
- How much power do data centers in Michigan use?
- Their combined disclosed capacity is about 6,517 MW.
- Where does this data come from?
- Every facility is compiled from public records and cited sources, including the FracTracker Alliance U.S. Data Centers Tracker and OpenStreetMap (© OpenStreetMap contributors, licensed ODbL). You can report an error on any facility page.
Counties in Michigan
All data is compiled from public records and cited sources. Report an error →